Stony Gorge Hazardous Fuels Reduction
The Stony Gorge Hazardous Fuels Reduction Project (Project) is a 121-acre fuels reduction project in western Glenn County, California. As of January 2023, the project is approximately 95% complete.
The Stony Gorge Hazardous Fuels Reduction Project (Project) is a 121-acre fuels reduction project in a critical location in western Glenn County, California. The Project addresses the risk of wildfire, reduces wildfire potential, and increases community resiliency. The project consists of vegetation clearance to reduce wildfire intensity, rate of spread and creates a fuel break above Elk Creek should a fire start in the public areas of Stony Gorge Reservoir & Campgrounds.
Stony Gorge Hazardous Fuels Reduction Site Map
The Project site is located east of the unincorporated community of Elk Creek; south of State Route 162 and directly north of the Stony Gorge Reservoir. The site is located approximately 1.5 hours north of Sacramento, west of I-5, and sits on the western side of the Sacramento Valley. Portions of sections 9 & 10 T20N, R3W, USGS 7.5’ Quadrangle Map: Elk Creek. Assessor Parcel Numbers: 021-190-019, 022-020-028 & 022-020-044. Lat 39.603; Lon: -122.532. The elevation of the site ranges from approximately 700 feet at its lowest point to approximately 1,100 feet at its highest point.
Pre Implementation
Pre Implementation April 2022
The objective was to remove invasive shrubs (including chaparral), brush and fallen trees. Mechanical treatment was utilized for most of the site (~100 acres) using a root rake or similar mechanized option. When mechanical operations were not feasible such as slopes greater than 40% or rocky terrain, manual / hand treatment was used; approximate 21 acres. Unhealthy or dead trees were removed; as well as previously fallen trees. Vegetation generated from operations was conservation burned. Once initial operations are completed; the following season spot spraying will be utilized as maintenance for the Project. Herbicide application will be utilized during this operation on any regrowth accumulated since the removal of invasive shrubs (including chaparral), brush and fallen trees; spot spray is anticipated to begin Spring 2023.
Pre Implementation Video Example
Pre Implementation May 2022
Planning Key Events
2020 - 2021
Project Identified
May 19, 2021
Application Submitted
November 22, 2021
CAL FIRE Agreement Executed
April 6, 2022
CEQA Completed
April 7, 2022
Request for Proposal Released
June 20, 2022
Contractor Selected: Cook Construction & Engineering Partnership
Implementation Phase
Implementation August 2022 (~25% Completion)
July 15, 2022
Mechanical Work Begins
August 2022
Hand Work Begins
September 2022
Mechanical Treatment Completed
Post Implementation September 2022
Before and After
Pre Implementation (left) March 2022 Post Implementation (right) May 2023. Use swiping tool to explore before and after.
Erosion Control
October 19, 2022
Aerial Seeding
Aerial Seeding October 2022
At the private landowner’s request, the Glenn County RCD coordinated the aerial seeding in order to help mitigate potential erosion as a result of the existing fuels reduction project where invasive shrubs (including chaparral) and brush were removed. Glenn County RCD partnered with the Natural Resources Conservation Service (NRCS) as well as U.C. Cooperative Extension (UCCE) to determine a viable seed mix for the project site; the landowner made the final decision, and an annual grass seed mix was flown onto the project site on October 19, 2022 by Regenald Michaud Aviation, LLC.
October 26, 2022
Straw Blowing
Straw Blowing October 2022
To further mitigate erosion, straw was blown on the project site in October 2022. The straw will help with erosion control practices as well as stabilize bare soils.
Post Implementation
December 6 & 7, 2022
Conservation/Pile Burning
Smoke production and Carbon emissions were mitigated by using conservation burn techniques as well as securing the required burn permit from Glenn County Air Pollution Control District. The residual biomaterial will be intergraded into the soil; subsequently increasing soil organic matter and Carbon sequester.
Visible Light Camera (left) Thermography Camera (right). Use swiping tool to explore conservation burn.
April 2023 Seeding Regrowth
Spring 2023 - July 2024
Herbicide Application and Project Maintenance
October 2024 Grazing Returned to Landscape
March 15, 2025
Project End Date
Landowner Partners
MAST FAMILY PARTNERSHIP
&
CLAY & JOANNE GWIN