Stoddard Road Project

February 2 – 16, 2023

Welcome

Thank you for visiting the Stoddard Road Project Open House. Here you will find information about the upcoming improvements. At the end, you will be able to provide feedback on the project.

Please continue scrolling down to browse through the full content of the website or toggle to different sections using the navigation bar above.

If you need printed materials mailed to you or need to make other arrangements to answer your questions, please call 208-387-6100 | TTY 1-800-377-3529 and we will be happy to help you.

This virtual open house will be open through February 16th.

Project Considerations

  • Safety for those that walk, bike, and drive
  • Bicyclist and pedestrian connectivity
  • Property and neighborhood impacts
  • Impacts to current and future traffic flow
  • Utilities


Example of Multi-use Pathway

Multi-Use Pathways

ACHD's Roadways to Bikeways Master Plan calls for more robust bike facilities along this type of roadway.

Multi-Use Pathways:

  • Two-way facilities meant to accommodate both pedestrians and bicyclists of a wide range of ages and abilities.
  • Provide more space between motorists and those walking and biking, which increases safety.
  • Are used on roads with higher speeds and traffic volumes.


Other Projects Planned in the Area

ACHD IFYWP Interactive Map


Traffic Volumes for Stoddard Road

Traffic Volumes

The numbers to the right represent the approximate number of vehicles using Stoddard Road between Victory Road and Overland Road during peak morning hour (left chart) and evening hour (right chart). The graphics show both the existing number of vehicles and the projected number of vehicles in the year 2045.


Project Timeline

2022

Design started

February 2023

Public input opportunity

2023 – 2024

Begin purchasing property necessary for project

TBD

Construction


What do you think?

Thank you for taking the time to review the information about the Stoddard Road Project. The next step is to tell us what you think!

Survey

Stoddard Road Community Feedback Survey

While your comments are always welcome, they can be best used if received by February 16, 2023.

After the comment period closes, ACHD will review and address comments received from the public.


Contact Us

David Rader, ACHD Project Manager

(208) 387-6271